2.1 Before commencing any checking or testing of a cable circuit and/or equipment the following
points should be adhered to:
2.2 Obtain any clearance to work or test permits that may be required from the appropriate
authority.
2.3 Ascertain that the cable and/or equipment to be tested is not 'alive' and is adequately 'earthed
down'.
2.4 In the eventuality of the cable and/or equipment not being 'earthed down' ensure that the
appropriate authority proves to your satisfaction that the cable/equipment is SAFE to work on
(i.e. circuit breakers and isolators open).
2.5 Set up the test equipment as close as practical to the cable and/or equipment to be tested.
(See Para 2.13).
2.6 Check that the cable and/or equipment to be tested is completely isolated from any other
equipment. (This does not include such things as post insulators and busbars which will not
be adversely affected by an applied high voltage.)
2
2.1 在開始對電纜線路和/或設(shè)備進行檢測或試驗前,應(yīng)注意滿足下列要求:
2.2 從主管部門獲取經(jīng)其認可的從業(yè)或試驗資格證明。
2.3 確定將被試驗的電纜和/或設(shè)備不是通路,并充分接地。
2.4 如電纜和/或設(shè)備有可能未充分接地的話,必須保證有關(guān)主管部門已確認在該電纜和/或設(shè)備上作業(yè)是安全的(如斷路開關(guān)和隔離裝置已斷開)。
2.5 設(shè)置試驗裝置,使其能最大程度且適用地滿足對電纜和/或設(shè)備的試驗。(見2.13段)
2.6對將被測的電纜和/或設(shè)備進行充分檢查,確保其已和其他設(shè)備完全斷開。(但不包括不會受高壓影響的器材,諸如柱形絕緣子和母線)